ENRE incorporates the Recreo–La Rioja interconnection into TRANSNOA’s transport system and sets its remuneration

The National Electricity Regulatory Entity (ENRE) ordered, through Resolution 17/2026, the incorporation into the transmission system under the jurisdiction of TRANSNOA S.A. of the facilities corresponding to the 132 kV double circuit between the La Rioja 500/132/33 kV Transformer Station and the La Rioja–Patquía High Voltage Line, identified as the “Recreo–La Rioja Interconnection” Expansion, and ordered its remuneration for operation and maintenance as of February 1, 2026.

Access  the complete text of the Resolution here.